Which times are used for Basic Date Scheduling of manufacturing planned orders in MRP? Select the correct options.

Enhance your SAP Production Planning and Manufacturing knowledge. Use flashcards and multiple choice questions with hints and explanations. Prepare effectively for your exam!

In the context of Basic Date Scheduling for manufacturing planned orders in Material Requirements Planning (MRP), it's essential to understand the role of various time factors and how they contribute to scheduling.

Setup time is the correct choice because it refers to the amount of time required to prepare a production process before actual manufacturing begins. This includes aligning machinery, gathering materials, and configuring tools necessary for production. Properly accounting for setup time is crucial, as it impacts the overall lead time for manufacturing processes. If setup time is not considered, planned orders may be scheduled inaccurately, leading to delays and inefficiencies in the production schedule.

The other options, while relevant to different aspects of production planning, do not play a direct role in the Basic Date Scheduling of manufacturing planned orders. Understanding the specific contributions of setup time helps reinforce the importance of each phase in the manufacturing execution timeline.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy